Current Road Works

Find out what's happening with minor road works within the City of Kalgoorlie-Boulder. The list below shows current and upcoming minor road works within the City. Traffic Management will be in place during works and the City will endeavour to minimise delays where possible.

Dates are subject to change based on the weather and contractor availability. 

Craig Road

Craig Road Resealing

Start Date: 16 May 2022

Completion Date: Mid to end July 2022

Profiling and sealing will take place between 16 and 17 May with asphalt sealing taking place from mid to end July 2022. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Memorial Drive

Memorial Drive Kerbing and Resealing

Start Date: 5 May 2022

Completion Date: Mid to end July 2022

Demolition of kerbing on both sides of the road will take place from 5 May to 13 May 2022. Profiling and sealing will take place between 17 May to 20 May 2022; with reestablishment of the kerbing following these works.

Asphalt sealing will take place from mid to end July 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Lionel Street

Lionel Street (Shotover to Holmes) Resealing

Start Date: 18 May 2022

Completion Date: Mid to end July 2022

Profiling and sealing will take place between 18 and 19 May 2022 with asphalt sealing taking place from mid to end July 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works.  The City will endeavour to minimise delays where possible.

George Street

George Street (Lane to Wilson) Resealing

Start Date: 20 May 2022

Completion Date: Mid to end July 2022

Profiling and sealing will take place between 20 to 21 May 2022 with asphalt sealing taking place from mid to end July 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works.  The City will endeavour to minimise delays where possible.

Oswald Street

Oswald Street (Oberthur to Davidson) Resealing

Start Date: 15 June 2022

Completion Date: 15 June 2022

Asphalt resealing works will take place on 15 June 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works.  The City will endeavour to minimise delays where possible.

Cheetham Street

Cheetham Street (Lane to Wilson) Resealing

Start Date: 20 June 2022

Completion Date: Mid to end July 2022

Profiling and sealing will take place between 20 June to 23 June 2022 with asphalt sealing taking place mid July 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works.  The City will endeavour to minimise delays where possible.

Burt Street

Burt Street (Gateacre to Gregory) Resealing

Start Date: 24 June 2022

Completion Date: Mid to end July 2022

Profiling and sealing will take place between 24 June to 25 Jul 2022 with asphalt sealing taking place from mid to end July 2022. Note - these dates are subject to change based on the weather and contractor availability.

Traffic Management will be in place during the above works.  The City will endeavour to minimise delays where possible.

Hutton Street

Hutton Street (Hutton & Dugan Intersection, Hutton & Hay Intersection) Resealing

Start Date: 16 June 2022

Completion Date: 8 July 2022

Profiling and sealing will take place 16 June to 17 June 2022 with asphalt sealing taking place 7 July to 8 July 2022. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Erin Court

Erin Court (Erin to Burt) Resealing

Start Date: 24 June 2022

Completion Date: 1 August 2022

Profiling and sealing will take place 24 June 2022 with asphalt sealing taking place 1 August 2022. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Shamrock Street & Outridge Terrace

Shamrock Street (Shamrock & Dugan Roundabout, Outridge Terrace) Resealing

Start Date: 21 June 2022

Completion Date: Mid July 2022

Profiling and sealing will take place 21 June to 24 June 2022 with asphalt sealing taking place mid July 2022. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Near Me

Discover when upcoming council works are near you. Simply start typing in your address or use your location settings on your mobile.

See what's around me


More Information

To view Major Council works and projects in the City, please visit www.ckbuneathed.com.au. If any further information is required, please contact the City on 08 9021 9600.