Current Road Works

The list below shows current and upcoming minor road works within the City. Traffic management will be in place during works and the City will endeavour to minimise delays where possible.

Dates are subject to change based on the weather and contractor availability. 

South Boulder

Lane & Hamilton Intersection

Start Date:  29 August 2022

Completion Date: 2 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Leviathan Street

Hamilton to Elbow

Start Date:  29 August 2022

Completion Date: 2 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Goldfields Hwy to Shannon

Start Date:  27 September 2022

Completion Date: 30 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Shannon to Waverly

Start Date:  3 October 2022

Completion Date: 7 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Hamilton to 88m West of TP

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Hamilton Street

Chaffers to Oroya

Start Date:  29 August 2022

Completion Date: 2 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Chaffers to Hamilton Elbow

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Vivian to Oroya

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Vivian Street

1m Strip Lane to Hamilton

Start Date: 29 August 2022

Completion Date: 2 September 2022

Profiling and sealing will take place between:

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Lane to Hamilton

Start Date:  29 August 2022

Completion Date: 2 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Columbia to Goldfields Hwy

Start Date:  27 September 2022

Completion Date: 30 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Patch East of Goldfields Hwy

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Patch West of Goldfields Hwy

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates, Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Columbia Street

Leviathan to Chaffers

Chaffers to Oroya

Oroya to Vivian

Vivian to Hopkins

Hopkins to Dwyer

Start Date: 12 September 2022

Completion Date: 16 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Dwyer to Outram

Start Date: 20 September 2022

Completion Date: 23 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Outram Street

Goldfields Hwy to Forrest + King Intersection

Start Date: 20 September 2022

Completion Date: 23 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Hopkins Street

Columbia to Goldfields Hwy

Start Date:  27 September 2022

Completion Date: 30 September 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Shannon to Waverly

Start Date:  31 October 2022

Completion Date: 4 November 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Shannon Street

Leviathan to Chaffers

Start Date:  3 October 2022

Completion Date: 7 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Outram Intersection to Shannon Intersection

Start Date: 2 October 2022

Completion Date: 9 October 2022

Profiling and sealing will take place between:.

Start Date:  31 October 2022

Completion Date: 4 November 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Vivian to Chaffers

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 7 November 2022

Completion Date: 11 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Chaffers Street

Goldfields Hwy to Shannon

Shannon to Waverly

Start Date:  3 October 2022

Completion Date: 7 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Columbia to Hamilton

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 17 October 2022

Completion Date: 21 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Oroya Street

Goldfields Hwy to Shannon

Start Date:  3 October 2022

Completion Date: 7 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Shannon to Waverly

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Hamilton to Cul-de-sac

Start Date:  17 October 2022

Completion Date: 21 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Columbia to Goldfields Hwy

Start Date: 2 October 2022

Completion Date: 17 October 2022

Asphalting will take place between:

Start Date: 21 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Columbia & Chaffers Intersection:

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 17 October 2022

Completion Date: 21 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Columbia & Leviathan Elbow

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 17 October 2022

Completion Date: 21 October 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Vivian & Columbia Intersection

Start Date: 2 October 2022

Completion Date: 9 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Hopkins & Columbia Intersection

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Dwyer Street

Columbia Intersection to Goldfields Hwy

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Dwyer & Goldfields Intersection West

Start Date: 10 October 2022

Completion Date: 14 October 2022

Profiling and sealing will take place between:

Start Date: 24 October 2022

Completion Date: 29 October 2022

Asphalting will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Outram & Waverly Intersection

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 31 October 2022

Completion Date: 4 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Waverly Street

Vivian & Oroya Intersections

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 31 October 2022

Completion Date: 4 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.


Chaffers & Leviathan Intersections

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 7 November 2022

Completion Date: 11 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Shannon & Leviathan Intersection

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 7 November 2022

Completion Date: 11 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Pirie Street

Shannon & Waverly Elbows

Start Date: 2 October 2022

Completion Date: 9 October 2022

Asphalting will take place between:

Start Date: 7 November 2022

Completion Date: 11 November 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

 

Other Areas

Cheetham Street

Lane to Wilson

Start Date:  22 August 2022

Completion Date: 27 August 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

Oswald Street

Oberthur St to Davidson St

Start Date:  29 August 2022

Completion Date: 30 August 2022

Profiling and sealing will take place between the above dates. Note - these dates are subject to change based on the weather and contractor availability. Traffic Management will be in place during the above works. The City will endeavour to minimise delays where possible.

 

Major Road Projects

Click here

Near Me

Discover when upcoming council works are near you. Simply start typing in your address or use your location settings on your mobile.

See what's around me

More Information

For more information on current road works, please contact the City on 08 9021 9600 or email mailbag@ckb.wa.gov.au